When you’re applying for a permit for a metal building, the drawings you submit can be just as important as the building itself. A set of generic plans may show the basic design and dimensions of a structure, but that doesn’t necessarily mean they contain everything your local permit office needs to approve the project. Depending on the location, building size, intended use, and local code requirements, the permitting authority may expect drawings that are specifically prepared for your property and project.
Understanding the distinction between the two before submitting your permit application can help you avoid delays, additional paperwork, or having to revise your plans after the application has already been submitted.
Key Highlights
- Generic drawings show the standard engineering for your building model. They are included with your order and they are free.
- Site-specific engineered drawings are calculated for your exact address and stamped by an engineer licensed in your state. They cost extra.
- Most permit offices that require an engineer's stamp will not accept generics, full stop.
- Anything occupied gets classified Risk Category II and always needs the stamped set.
- Drawings are ordered after your deposit, and the engineer typically takes 21 to 25 business days.
- Your permit review starts after the drawings arrive, not alongside them. Plan the calendar accordingly.
- Not sure which one your county wants? Call (208) 572-1441 with your address and we will check before you order.
What Each Drawing Set Actually is
Generic drawings are the standard engineering package for the building you bought. Dimensions, frame layout, panel details, and the loads the model is built to at standard ratings. They describe how the building goes together and what it’s rated for. None of it is tied to your parcel, your soil, your county's snow number, or your jurisdiction, and there is no engineer's seal on them for your state.
Plenty of counties are fine with that. If you are putting up an unoccupied barn outside city limits in a county with no meaningful snow load, generics are often all anybody asks to see. They come with your order at no cost.
Site-specific engineered drawings are a different document. An engineer licensed in your state takes your exact building, your exact address, and the wind speed, ground snow load, seismic category, and exposure for that spot, then runs the calculations and stamps the result. The output is a set of sheets showing how your building performs at your location, plus the foundation and anchoring details that go with it.
That stamp is the whole point. It is a licensed professional putting their name on the statement that this building, on this lot, meets the code your county enforces. That is what a plan reviewer is looking for when they say they need engineered drawings.
Which One Your Permit Office Will Accept
Four things decide it, and only one of them is up to you.
-
Whether anyone will occupy the building
If the building is going to be lived in, slept in, or occupied under a permit, it gets classified as Risk Category II, and that means stamped site-specific drawings every time. A barndominium shell, a shop with a bathroom, a commercial space, an office. It does not matter how small it is. Our steel frame barndominium guide covers what that classification changes, and you can see the shells we build on the barndominium page.
-
Your county's snow and wind numbers
Where ground snow load is high, generic ratings often do not reach far enough and the county wants calculations for your elevation and exposure. Same with high wind zones and coastal counties. We pull your address's numbers as part of quoting, so we usually know before you do whether the standard package covers you. The snow and wind load page shows how those ratings work, and our breakdown of how codes and snow loads move the price covers the cost side.
-
Your jurisdiction, which is not the same as your state
Requirements are set county by county, and often differently inside city limits than outside them. Two neighbors on opposite sides of the same road can face different rules, and we have had that exact call more than once. Our state-by-state permit requirements guide is the starting point, and there is a deeper look at one market in our Idaho permits and plan costs post.
-
Size and what is holding the roof up
Bigger buildings, wider clear spans, and anything commercial push toward stamped drawings even in relaxed jurisdictions. A 20-foot carport and a 60-foot-wide shop are not the same conversation with a plan reviewer.
"Give us your install address before you order and we will find out what your building department requires. It takes one phone call on our end and saves you a month on yours. Call (208) 572-1441."
Planning a wider shop or commercial building? Browse our commercial metal buildings or see the 50x50 clear-span metal building for a real-world clear-span configuration.
What Is Actually Inside A Site-Specific Set
A stamped set includes the foundation plan, which shows slab dimensions, footing sizes and depths, and reinforcement. It includes the anchor bolt layout, which tells your concrete contractor exactly where the anchors go before the pour rather than after. It includes base rail and connection details showing how the frame ties to the foundation. And it includes the edge condition, meaning whether your slab is poured flush or with a notch, sometimes called a sheeting ledge, for the panels to drop over.
The base trim that closes the gap at the bottom of your wall gets bent in the shop to match your slab edge. If your drawings show a lip and your contractor pours flush, or the other way around, the trim does not fit and you find out on install day. Read that sheet, hand it to your concrete guy, and tell us what it says. Our site preparation page covers the rest of what the crew needs from the site, and the 40x60 slab cost guide shows what a foundation on a larger footprint involves.
Generic drawings will not give you any of that at your specific dimensions. They will get a simple building past a relaxed county, and they will not tell your concrete contractor where to set anchors.
Generic Vs Site-Specific, Side By Side
| Factor | Generic drawings | Site-specific engineered drawings |
|---|---|---|
| Engineer's stamp | No | Yes, licensed in your state |
| Tied to your address | No | Yes |
| Local loads calculated | Standard ratings only | Your wind, snow, seismic, exposure |
| Foundation and anchor layout | General guidance | Specific to your building |
| Accepted for occupied buildings | No | Yes |
| Cost | Included with your order | Quoted separately, varies by size and location |
| Time to receive | Days after deposit | Roughly 21 to 25 business days |
| Typical use | Unoccupied ag and storage in relaxed counties | Anything permitted, occupied, large, or in a high-load county |
Where Drawings Sit In Your Timeline
Drawings get ordered after your deposit, not before. Once the deposit is in, your order moves to our drawings department, they call you to confirm every detail of the building, and the package goes to the engineer. If you need the site-specific set, that’s when it gets quoted and paid for.
The engineer typically takes 21 to 25 business days. That is business days, so call it four to five weeks on a calendar. When the stamped set comes back, we send it to you, and then you take it to your building department and permit review starts. Review is its own timeline, set by your county, and it runs after the engineer, not at the same time.
Only once you have the permit and the site is ready does the install clock start. Add it up and a permitted building can run a few months from deposit to install, with most of that spent waiting on other people. Buyers who understand this at the start are relaxed about it. Buyers who find out in week six think somebody is stalling them.
The one thing that speeds this up is deciding early. Every change to the building after the drawings go to the engineer restarts part of that clock. Lock your dimensions, your leg height, your openings, and your lean-tos before the package leaves. Our installation timeline breakdown lays out the whole sequence, and the ordering process page covers what happens at each payment stage.
Lock your building configuration before engineering starts. Use the 3D Building Designer to configure your size, roof style, doors, windows, colors, and other options before the drawing package moves forward.
What Stamped Drawings Cost And Why It Varies
There is no flat price on site-specific engineering, and anyone quoting you one over the phone before they know your details is guessing.
The cost moves with the size and complexity of the building, your state, and the risk category. A simple garage in a mild county is at one end. A wide-span occupied building in high snow country with lean-tos attached is at the other, because every attached structure is more calculation. Lean-tos in particular are often engineered as their own elements, so a building with two of them is not the same job as a building with none.
Two practical notes. First, budget for it as a separate line rather than assuming it is folded into the building price, because it is not. Second, if the engineering cost is what is squeezing you, financing the building itself frees up the cash. Terms are on the financing page.
Still comparing certification requirements? Read our certified metal building permits guide for more detail on wind loads, snow loads, certification, and permit-ready engineering.
Four Mistakes That Cost People Time
-
Assuming your neighbor's answer applies to you.
Requirements change across county lines and city limits. Ask your own building department, or give us the address and we will ask.
-
Waiting to ask about permits until after the deposit.
Call your county before you order. A five-minute conversation tells you whether you need the stamped set, which tells you what your real timeline is.
-
Changing the building after drawings are ordered.
Adding a door, moving a wall, or bolting on a lean-to after the package is with the engineer means revisions and more waiting. Get the whole build sheet right first. Configurations for metal garages, metal barns, and workshop buildings are worth reviewing before you commit.
-
Pouring concrete before the drawings arrive.
The anchor bolt layout lives in that set. Pour first and you are drilling into cured concrete, or worse, your anchors are in the wrong places. Wait for the sheets.
Sorting This Out Before You Order
The right drawings can make the permitting process much easier, but the requirements ultimately depend on your local jurisdiction and the specifics of your building project. Generic drawings can be useful for showing the basic design of a structure, but they may not provide the site-specific information a permit office needs to verify that the building meets local codes.
Site-specific engineered drawings provide a more complete picture by accounting for the conditions and requirements associated with your particular property.
Design your building in 3D at EngineeredMetalBuildings.com, or call (208) 572-1441 with your address and what the building is for. We will check your county's requirements, pull your loads, and tell you what your real timeline looks like before you put a dollar down. Coverage is on our service area page.
Frequently Asked Questions
No. Drawings are produced after the deposit, once your order moves to our drawings department and every detail of the building is confirmed.
They should not. The anchor bolt layout, footing sizes, and slab edge detail all live in the drawing set. Pouring first means either drilling into cured concrete or discovering the anchors are in the wrong spots.
Yes. Anything occupied is classified Risk Category II at minimum, which requires stamped site-specific drawings regardless of how small the building is. A 24-foot-wide shell someone will live in needs the same document a much larger one does.
It varies by building size, complexity, state, and risk category, so it gets quoted after your order rather than at first contact.
Typically 21 to 25 business days from the engineer, which is roughly four to five weeks on a calendar.
In some counties, yes, usually for unoccupied ag and storage buildings outside city limits where snow and wind loads are modest. Where a plan reviewer asks for an engineer's stamp, generics will not be accepted. The only reliable way to know is to ask your building department with your address in hand, or call (208) 572-1441 and we will check for you.
Generic drawings show the standard engineering for your building model at standard load ratings. Site-specific engineered drawings are calculated for your exact address using your county's wind speed, ground snow load, seismic category, and exposure, then stamped by an engineer licensed in your state.